Construction Expansion · Denver, CO

How a $2.5M Construction Expansion Was Structured Across Three Layers

Moving from residential to commercial is not one purchase. It is a building, a fleet, and a bonding line, and they have to arrive together or none of them works. The structure that funded it sent each piece to the lender that prices it.

Request a Financing Review

The capital stack

No single lender wanted a building, a fleet, and a bonding line on one contractor. Three lenders underwriting three pieces funded it in 24 days

$2.5M
Funded
24 days
To close
3
Layers
1
Application

The Structure

Capital Stack Breakdown for a $2.5M Construction Expansion

Three products, one file, three different kinds of collateral. The shop and yard are real estate and finance as owner-occupied property. The excavators and loaders are equipment and secure themselves. The bonding and mobilization capital is neither — it is cash the surety and the first commercial job both require before a dollar comes back. Blended into one bank loan, the whole thing gets priced at the riskiest layer’s terms. Separated, each piece funds the way it should.

No single lender wanted a building, a fleet, and a bonding line on one contractor. Three lenders underwriting three pieces funded it in 24 days

Representative structure

Owner-occupied commercial real estate$1.4M
Equipment financing$800K
Working capital$300K
Funded together$2.5M
LayerAmountWhat it covered
Owner-occupied commercial real estate$1.4MThe shop and yard, underwritten against the property and the contractor’s revenue, roughly 10% down
Equipment financing$800KExcavators and loaders across two builders — each machine securing its own piece
Working capital$300KBonding capacity, mobilization on the first commercial job, and payroll before the first pay application
Total$2.5MFunded together on one application

Larger expansions fund the same way when revenue, cash flow, and story qualify.

The Transaction

What the Contractor Was Building Toward

Bobby Friel, Founder of Basecamp Funding

Bobby Friel

Founder, Basecamp Funding

Every residential contractor who has looked seriously at commercial work has found the same thing: the bid is the easy part. Getting on the list of subs a general contractor will even send the bid to is the hard part, and it takes a yard, iron, and a bond.

A contractor had built a solid residential business and wanted the commercial work — which meant three things at once: a shop and yard to run from, heavier iron to bid with, and the bonding capacity general contractors require before they let you quote. No single lender wanted all three. The specialist desk structured a $2.5M stack: owner-occupied real estate financing for the shop and yard, an equipment line for excavators and loaders, and working capital for bonding and mobilization. One application, the right lender on each layer, funded in 24 days. The contractor bid its first commercial job the following month.

Underwriting

How Construction Business Financing for an Expansion Actually Works

A bank underwrites the contractor as one loan. This structure underwrote the building, the iron, and the bonding line as three — and that is why one path stalls on the piece the bank likes least and the other funds all of it.

The Bank

What a bank sees.

A residential contractor with a thin balance sheet asking for $2.5M across a property, a fleet, and cash for bonding, with no commercial revenue yet to point to. It prices the whole request at the risk of the working-capital piece, asks for 25% down on the real estate, and wants the commercial contracts before it funds the capacity to win them.

This Structure

What this structure saw.

Three assets, three lenders, each pricing what it holds every day. A building the contractor will occupy. Machines with a resale market. And a bonding line that, once in place, is the gate to a category of work priced against a shortlist instead of against everyone with a truck.

Why the Shop and Yard Finance as Real Estate, Not as Overhead

A commercial contractor needs a place to stage equipment, store material, and run a crew from — and a bank folding that purchase into a business loan treats it as overhead. As owner-occupied commercial real estate, it is underwritten against the property and the contractor’s revenue, at roughly 10% down. $1.4M of the expansion resolved against a building the business will still occupy in ten years.

Why the Iron Finances Itself

Excavators and loaders from more than one builder do not come from one dealer, and a captive finance arm handles only its own brand. An independent equipment structure covered the whole fleet in one facility — each machine titled, appraisable, and securing its own piece. $800K resolved against the equipment before anyone argued about the contractor’s balance sheet.

Bonding Is the Layer Nobody Explains

General contractors qualify their subs before the bid, and a performance bond is the gate. A surety sets bonding capacity on working capital — cash and near-cash on the balance sheet — and a residential contractor moving up typically has too little of it. The $300K working-capital layer did two things: it raised the bonding line the surety would write, and it funded mobilization on the first commercial job, where the contractor pays crew and material for weeks before the first pay application is approved.

Why All Three Had to Close Together

A yard without iron is a parking lot. Iron without a bond is a fleet that cannot bid. A bond without a yard is capacity with nowhere to stage. The expansion only works if all three arrive at once, and that is precisely what a single bank loan cannot do — it stalls on the piece the committee likes least and the other two wait. Twenty-four days was three lenders working in parallel on one closing calendar.

What Commercial Work Actually Buys

Residential work is priced job to job against everyone with a truck. Commercial work is priced against a shortlist of qualified subs, and once a contractor is on that list, the same yard, the same fleet, and the same bonding line bid the next project and the one after that. The expansion is not a bigger residential business. It is a different business with different margins.

Run the arithmetic your own way: what does one commercial project net you against the same crew-months of residential work, and how many were you not allowed to bid last year because the bond wasn’t there?

For most contractors at this scale, the answer is that the first commercial job covers the cost of the structure and everything after that is a category the business could not enter before. That is a different question than whether a bank wants to fund capacity before the contracts exist.

The Products

The Products That Funded This Transaction

ProductRole here
Commercial Real EstateThe shop and yard, underwritten as owner-occupied against the property
Equipment FinancingExcavators and loaders across two builders, each securing its own piece
Working CapitalBonding capacity and mobilization on the first commercial job

Financing this whole sector: Construction Financing

The Result

What Changed After Close

3
Layers, one closing
24 days
Application to funded
Raised
Bonding capacity
Month one
First commercial bid

Start Here

See What Your Expansion Structures Look Like

Sixty seconds, no documents, and a soft-pull review. If moving into commercial work means a building, iron, and a bond all at once, this is where you find out what the structure looks like.

~60-second review · Soft-pull, FICO untouched · No obligation

No obligation. Soft-pull review — your FICO stays untouched.

Related

Similar Structures

Representative scenarios — illustrative, anonymized figures, not specific client transactions.

FAQ

Construction Business Financing for a Commercial Expansion — Questions, Answered

How do you finance a construction company’s move into commercial work?

Rarely with one loan, because the expansion is three different kinds of asset. A shop and yard finance as owner-occupied real estate. Excavators and loaders finance as equipment. Bonding capacity and mobilization finance as working capital. Sending each to the lender that prices it — and closing all three together — is what makes the full number reachable.

Why won’t a bank fund a shop, a fleet, and bonding capital together?

Because it prices the whole request at the risk of the piece it likes least — usually the working capital — and it wants commercial contracts before funding the capacity to win them. That is backwards: a general contractor won’t send the bid to a sub without the yard, the iron, and the bond already in place.

How does bonding capacity get financed?

Indirectly. A surety sets a contractor’s bonding line on working capital — cash and near-cash on the balance sheet. A working-capital layer raises that figure, which raises the bond the surety will write, which is the gate to commercial bids. The same layer typically funds mobilization on the first job, where crew and material are paid weeks before the first pay application.

How much do you need down to buy a contractor’s shop and yard?

As owner-occupied commercial real estate, typically around 10% when revenue and deposit history support it — versus 25% to 30% on a bank’s standard track. On $1.4M, that difference is money that goes into the iron and the bond instead of the closing.

Can you finance equipment from different builders in one loan?

Yes, and for a contractor building a fleet it is the point. A captive finance arm handles its own brand only. An independent equipment structure covers excavators from one builder and loaders from another in one facility with one closing, each machine securing its own piece.

Can you fund a construction expansion without an SBA loan?

Yes, and when the three pieces have to close together, a conventional stack is usually the faster path. SBA programs can cover parts of an expansion, but the timeline and the single-lender structure rarely fit a building, a fleet, and a bond on one calendar. This structure funded in 24 days across three lenders. The trade-offs are real, and a specialist should walk you through both.

How long does it take to fund a contractor expansion?

The real estate sets the pace — appraisal, title, survey — so weeks, not days. Twenty-four days is fast, and it required three lenders working in parallel on one closing calendar with a file ready before the clock started: twelve months of bank statements, the purchase contract, the equipment specified, and the surety’s working-capital requirement in writing.

One Last Question

The bid was never the hard part. Getting on the list was.

A yard, a fleet, and a bonding line each price differently. Structured together and closed together, they put a residential contractor on the commercial shortlist in 24 days.

Request a Financing Review →

~60-second soft-pull review · Real term sheets, not estimates · Underwritten on your revenue, your building, and your iron